Foundation


See Final Update

We are using Superior Walls for the walkout-basement. Since much of the walls will be visible above grade, we chose a large stamped-brick pattern for the exterior of these cast-concrete panels.



August 23, 2010

The precast foundation panels arrived on a flatbed truck, followed by a large crane.

Superior Walls panels rest on a compacted gravel base, not on traditional concrete footings. Here a worker compacts the gravel around the perimeter of the circle.

With the gravel compacted, the crew used the crane to place each panel in its designated position. Here's the first panel being lowered. It has no stamped-brick pattern because it's inside the yard equipment room.

The fourth panel came 17 minutes later. Exterior wall panels have the stamped-brick pattern.

29 minutes after that, half the panels were in place.

Two hours after starting, the final (18th) panel under the Deltec shell was being set. Remaining to be set were the six panels for the stairwell and yard equipment room bump-out.

One edge of the bump-out's large end panel was slightly deformed, and required grinding to shape.

The grinding took some time, but an hour later the end panel was in place and the final side panel was lowered.

All 24 panels in only 5½ hours.



August 27, 2010

Four days after the basement walls were placed, the concrete crew arrived, and poured and finished the floor slab.



Page Top

Updated May 23, 2023